2007
Report of the
Harbormaster/
Natural Resources Department
As I
begin to write this, my 35th annual report, it feels like only yesterday
I began working at
Piling replacement
As explained in last years report in an emergency plan using Special Town Meeting funds, 23 steel pilings at Saquatucket Harbor and 15 steel pilings at Wychmere Harbor were replaced with 40’ x 12” Pearson UV resistant fiberglass pilings at a project cost of $117,000 in late June. Fiberglass pilings are a new technology and they are desirable due to their large bending moment and ability to sustain huge sideward force. This work replaced all of the 14 year old “steelies” which fell woefully short of their life expectancy of at least thirty years. More piling work is needed replacing an additional 15 steel pilings that were added later in the dock system. We will no longer think about white oak or steel as a choice for tie-off pilings, and only consider limited use of CCA treated southern yellow pine as an option alternative.
HARBOR INCOME
FY07 +/- FY06
Saquatucket
Dockage 433,157 -4.20% 452,148
Visitor
Dockage 155,758 10.37% 141,599
Mooring
Permit Fee 63,130 -0.23% 63,275
Ramp
Fee Collected 31,919 22.61% 26,034
Allen
Town Dock 19,549 -11.26% 22,031
Offload
Permit Fee 19,534 -42.23% 33,816
Fuel
Commission 18,994 19.92% 15,838
Electric
Use
18,354 -28.08% 25,519
List
Waiting Fee 17,175 6.38% 16,145
Shellfish
Permits*
5,742 149.12% 2,093
Ice
Receipts 1,882 -16.36% 2,250
MSA
Fee 800
33.33% 600
Restaurant
Tie-up
461 9.76% 420
Mooring
Drop/Haul 100 0
Copying
& Fax 83 167% 31
Trap
Permit 25
0
Allen
Hrbr Storage 12,445 10.00% 11,314
Refund (916)
________ ______ ________
TOTAL RECEIPTS $816,541 -2.51% $837,562
FY07
Breakout: GEN FUND WIF Shellfish
$746,869 $63,930 $5,742
HARBOR EXPENSES
Expenses
(actual) 79,126 8.87% 72,677
Salaries
& Wages 218,178 0.17% 217,810
_______ ______ ________
297,304 2.35%
290,487
*all shellfish permits entirely sold at Harbormasters
Office instead of Town Hall beginning FY07
Out of the ordinary
Occurrences
On March 15th, the Fire
Department was able to put out an early morning boat fire onboard MISS MORGAN a
35’ codfish boat at
In a bizarre late night accident, three
days after the boat fire, a driver in an F350 pickup truck traveling at a high rate of speed drove
off the end of the Town Pier smashing out the batter pile and damaging the cap
log. The female driver was able to extricate herself from the vehicle which
floated out further before sinking to the bottom in 12’. She swam back nearly 300’ to the shoreline in icy water (37°F) , a nearly impossible feat. She then broke into a nearby
fishing shanty to keep warm. Authorities were unable to charge the driver because
there were no witnesses at the moment of the accident. The town should know
that our insurance agent
Workshop and Parcels
The
Board of Selectmen voted to allow town meeting to decide whether more than
two-and-a-half acres of town land behind our workshop on
Due to its convenient location to
the three harbors and its layout, the workshop at
Harbor Redevelopment
This was the first full season
that
The fuel dock closure had left us
with some extra bulkhead space. We made use of it by moving the town’s only
marine sewage pump-out station for easier deep water access. At the same time,
we are now providing space at no charge to the Fire Department for a newly
obtained hard bottom inflatable three-season rescue boat.
Consideration is still in the works for obtaining the adjacent Downey Property along Route 28. This would become additional marina parking, possible boat storage and/or an active rack moored boats which would be fork-lifted to the bulkhead. Relocating the Freedom Cruise Line and the charter boat fleet within the footprint of the marina is also worth consideration. The Capital Outlay Committee has recommended we postpone buying this land and instead has agreed that an overall planning study is needed to understand just how Harwich needs to spend additional funds to accommodate and improve the working harbor(s).
Shellfish Laboratory
The Town has been in the business
of rearing shellfish in the laboratory located at
The Harwich Shellfish Lab was
also the site of our 10th high school summer aquaculture internship
program. The six week program, managed
by
2007 Shellfish Permits Sold
Resident Family 300 $3000
Non-Resident Family 66 $1980
Commercial 6 $240
Seniors 84 $252
One-Day
Non-Resident 18 $270
TOTAL 474 $5,742
Our quahog seed continues to be tested prior to seeding (per order of the Massachusetts Division of Marine Fisheries) for Dermo, QPX, and an array of other harmful parasites. This has been the seventh consecutive year for such testing and once again our shellfish received a clean bill of health from the Shellfish Pathology lab in Woods Hole, Ma.
Oysters were added to our rearing
program at the shellfish lab this year. This
year we purchased 100,000 small oysters (4-5mm) and grew them in our upwellers. The
oysters were a success and grew to an average of 2 inches in size and were
seeded in
Dedicated Volunteers
To patrol the local shellfishing flats we again relied on the assistance
provided by our dedicated group of volunteer shellfish wardens.
The Harwich Natural Resources
Department continues to receive assistance with many of our projects from
volunteers. A great deal of thanks is
extended to
Shellfish Harvest Survey
This was our second year we asked shellfishermen to fill out a shellfishing survey when obtaining their license at the Harbormaster’s office. Last year we received 82 completed surveys, but since all permits are now being sold at the Harbormaster/Natural Resources Dept. office we received 219 completed surveys. From those surveys we were able to compile the following:
Average days someone went shellfishing in 2006………………6.84 days
Average # buckets of quahogs taken in 2006/shellfisherman…...3.51 (10qts)
Average #buckets of oysters taken in 2006/shellfisherman….…..0.09 (10qts)
Average #buckets of softshells taken in 2006/shellfisherman……1.24 (10qts)
Note: When someone buys a permit we get the previous year’s survey results. The 2007 data will be available after everyone has purchased their 2008 license and will be included in the next year’s town report.
Herring Run
The Herring Run remains closed
due to the moratorium enacted by the Division of Marine Fisheries on the taking
of herring anywhere in
The moratorium however did not
deter the Natural Resources Department, along with the many Americorps
volunteers, to keep the
Harwich Water Quality
Task Force (volunteers)
Local water quality monitoring
continued in full force. Samples were collected from
This was the second time, pilot Heinz Proft and Task Force volunteers were able to conduct a pond fly-over photographing each pond for comparison and to understand clarity issues of each of our ponds that are threatened by elevated nitrogen and phosphate levels from build-out. In April, the Watershed Association of South Harwich with some support from Harwich installed a Solar Bee@, a solar powered pond water lift pump, in the deep end of Skinequit Pond to help aerate the 18 acre lake and try and improve clarity. . September’s flight showed Skinequit Pond particularly murky with an algae bloom.
Water Sampling Programs
Harwich also continued its’ water
quality sampling as part of the Pleasant Bay Resource Management Alliance. We
would like to thank Al and Barbara Williams,
Oceanographic data collection from Nantucket Sound was also hindered this summer due to fact our collecting platform, Harbormaster vessel Commander, was under repair. Next summer we plan to resume collecting such data as water temperature, water salinity, dissolved oxygen, and turbidity.
Oyster Creek Shellfish Area
A group of neighbors calling
themselves the Oyster Creek Preservation Society was given permission by the
States highest court to move ahead with plans to dredge a narrow tidal inlet
despite objections from the town of
The
town's Conservation Commission denied their request in a late decision in October
2003 based upon reports from Division of Marine Fisheries and this office
lauding the productivity of the Oyster Creek as a shellfishing
area that must not be tampered with. The
The
dredging still must be approved by other agencies, including the US Army Corps
of Engineers and the state water quality program, before it can move forward.
Oyster Creek has a long history as the most productive family shellfishing area that Harwich has. Deepening the creek
will not only remove the beds but make most of the area off limits to shellfishing. This will most likely invite further erosion
to the banks on either side of the creek. Abutters on the south side to the
tight channel are seeking to stabilize the banks in defensive of the erosion
the anticipated dredging will effect.
Dredging Projects and Beach Restoration
Long
after the county dredge Codfish had finished clearing a shoal from the
The DEP Bureau of Resource Protection sent a letter to Harbormaster Thomas Leach saying the department was appealing the local commission’s ruling because it did not address concerns raised by the Natural Heritage and Endangered Species Program (NHESP). Specifically, NHESP indicated that “No beach nourishment work, including placement or removal of pipes or other equipment, and placement, dewatering and grading of dredged materials, shall occur between April 1 and Aug. 31” in order to avoid adverse effects on the Resource Area Habitats of state-listed shorebirds. This effectively closes the door on all dredging projects between January 1st and August 31st. However, an appeal by our conservation agent John Chatham has removed this closure pending examination of the resources involved on a case by case basis. The NHESP letter cites concerns about two state-listed shorebird species, the common tern and the roseate tern, stating the birds would be harmed by the shoreline disruption associated with dredging. It also indicates that when dredged sand is used to nourish a beach, it must be placed at a very shallow slope ratio of 10:1.
Private participation in dredging
and beach restoration projects were in the forefront this year, beginning with a very late 2006 project removing
5,400 cu.yds of material from Round Cove channel to
rebuild the barrier beach. It continues to be threatened by over-wash tides due
to the Chatham Break. 2,200 yards of this material was paid for and placed on Wequasett Inn beach. A new breach in
One of our most aggressive channel dredging operations in
recent years brought sand to
Members of the Wyndemere Beach
Association now have enough beach to stretch towels
and blankets. The beach association received 2,222 cubic yards of sand, paid
for out of pocket through the dredging gift. We hope private shorefront
property owners and associations will make more use of this idea as we continue
to plow town money into an overall permitting scheme. Restoring the public
beach at
This effort to grow Harwich shoreline by getting sand back
onto beaches both public and private is critical to protection of property and
the enjoyment of the beach. We continue to forge ahead with a broad permit plan that will give Harwich the opportunity to
take sand from any of its channels and place the sand on almost any beach in
Harwich. This year we spent $85,286.24 on permitting which chewed heavily into
our dredging reserve accounts. $146,623 was spent on the actual moving of a
total 21,722 cu.yds.
of material. The Town received $56,750
in gifts toward dredging to cover the differences. At years end, the County
dredge returned to Harwich with its new booster barge to relay approximately
5,300 cu.yds of channel sand at $11 per yard from
between the Saquatucket Harbor jetties to Red River Beach west end and
bathhouse area. Cost of this phase when the bill is paid will have exhausted
our dredging reserves.
Water Metering
A new
water metering station was established on the west bank of
for
understanding the movement or restriction of alewives within the river system.
Live data can be read from the website.
The project description identified the need to remove between 20,000 to 42,000 cubic yards of material composed of organic sludge that is the byproduct of the marshes and stream to the north and nitrogen groundwater inflows. The organic material limits disposal of the dredge spoil to off-site locations. The assessment identifies six inch to one foot-thick organic mat on top of more than six feet of consolidated organic material. This material also has no structural qualities, so that upon dredging it would continue to slip into the dredge area, requiring more material to be removed. The only conclusion is that the material will have to be de-watered and disposed of off-site, either in a landfill, as composting material, or as non-structural fill.
An analysis of four dredge options for 30,000 cubic yards runs from $1,424,900 to $2,924,900. The bucket dredging estimate is $1,725,000. The potential for issuing a general obligation bond for waterways maintenance projects, much the same way some highway department and municipal golf course projects are now funded is being discussed. The Capital Outlay Plan includes undertaking this work by FY11. The plan also calls for immediate replacement of more harbor pilings, a new float system for Allen harbor, and for an engineering study of the total harbor needs analyzing where and how we need to make changes and improvements in this infrastructure.
Boat Ramp Repairs
In October, Robert B. Our
Department Support
The Harbormasters Office is indebted to the Highway
Department for all their great support throughout this year. Many thanks to Linc, Chris, Collin, Charlie, John, Buddy, Walter, Boo, and
Judy for all their help from reconditioning our vehicles, remodeling our
buildings, plowing the lots, mowing our lawn, backing us with man power where
we needed it, to even keeping the heads presentable at Wychmere and Allen
Harbor. Their ability to move a huge volume of beach sand across town was
incredible. It shows that
Heinz and I wish to thank harbor clerk
The Natural Resources Department lost a great friend this
year in the passing of herring warden and assistant harbormaster Garry
Stephens. Garry loved boating, and volunteered his free time to protecting the
alewife run. He was also credited with a dramatic boating rescue of Jeffrey
McCarty whose boat had swamped on the
Respectfully,
Thomas E. Leach, BS, CHM Harbormaster/
Natural Resources Director
Heinz M. Proft, BS, MS Assistant